Dozing To Restore Highway 132 (Day 14) - Progress on Highway 132 bulldozing - two weeks in work is progressing towards grading the lava rock from the 2018 eruption to form a new roadway. Hawaii County Research and Development director Diane Ley presented "major expenditures and encumbrances" associated with road recovery efforts, included past and future work. Here is the breakdown: Highway 137 Temporary Access COST: $200K (via Governor’s $12 Mil) Kipuka Access COST: $12K (via Ordinance 19-22) Highway 132 Temporary Access COST: $12.7 Mil (via Reimbursement Federal Highway Administration) Pohoiki Road Temporary Access COST: $31.5 Mil (via FEMA Public Assistance) https://youtu.be/tS4A1NLbxSw